| LINE | Name | Country | City | Regional Rail | |||
| Line 4 Phase 1 | CN | Xuzhou | No | ||||
| CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
| 5 years | 25.4 | 25.4 | 100% | 19 | Plan | ||
| COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
| 17354.0 | CNY | 0.24 | 2020 | 4133.7 | 162.7 | Plan | |
| REFERENCE | https://www.ndrc.gov.cn/xxgk/zcfb/tz/202002/P020200210345113822478.pdf | ||||||
| NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. |
||||||
| Go to Xuzhou city page. | |||||||