| LINE | Name | Country | City | Regional Rail | |||
| Line 13 Phase 1 | CN | Guangzhou | No | ||||
| CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
| 2013 | 2017 | 27.03 | 27.03 | 100% | 11 | Media | |
| COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
| 19038.0 | CNY | 0.27 | 2013 | 5196.0 | 192.2 | Media | |
| REFERENCE | http://www.dcement.com/Article/201310/117609.html | ||||||
| NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. |
||||||
| Go to Guangzhou city page. | |||||||