| LINE | Name | Country | City | Regional Rail | |||
| Line 8 Phase 3 South | CN | Beijing | No | ||||
| CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
| 2014 | 2018 | 13.0 | 13.0 | 100% | 11 | Measured | |
| COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
| CNY | 0.27 | 2014 | Media | ||||
| REFERENCE | https://www.bjsubway.com/news/ghjs/2013-12-30/1316.html | ||||||
| NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. |
||||||
| Go to Beijing city page. | |||||||