LINE | Name | Country | City | Regional Rail | |||
Phase 3 (Red Line Extension/Route 2020) | AE | Dubai | No | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
2016 | 2020 | 15.0 | 3.2 | 21% | 7 | Trade | |
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
2900.0 | USD | 1.9 | 2016 | 5510.0 | 367.3 | Media | |
REFERENCE | https://www.railway-technology.com/projects/route-2020-dubai/ | ||||||
NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. |
||||||