LINE | Name | Country | City | Regional Rail | |||
Line 10 Phase 1 | CN | Hangzhou | No | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
2018 | 2022 | 15.9 | 15.9 | 100% | 13 | Plan | |
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
13109.0 | CNY | 0.25 | 2016 | 3286.3 | 206.7 | Plan | |
REFERENCE | https://www.ndrc.gov.cn/xxgk/zcfb/ghwb/201612/W020190905497886107757.pdf | ||||||
NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. |
||||||
Go to Hangzhou city page. |