LINE Name Country City Regional Rail
Line 7 CN Hangzhou No
CONSTRUCTION DETAILS Start year End year Length (in km) Tunnel (in km) Tunnel Stations Source
2017 2021 45.0 22 Plan
COST INFORMATION Cost (in M) Currency PPP rate Year PPP Real cost (in M$) Cost/km (in M$) Source
28997.0 CNY 0.25 2016 7269.2 161.5 Plan
REFERENCE https://www.ndrc.gov.cn/xxgk/zcfb/ghwb/201612/W020190905497886107757.pdf
NOTES Sections of the line constructed in trench are represented with the same line style as the at-grade sections.
The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project.