LINE | Name | Country | City | Regional Rail | |||
Line 8 Phase 1 | CN | Hefei | No | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
not started | 23.0 | 23.0 | 100% | 12 | Plan | ||
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
16201.0 | CNY | 0.24 | 2020 | 3859.1 | 167.8 | Plan | |
REFERENCE | http://zfxxgk.ndrc.gov.cn/web/iteminfo.jsp?id=16921 | ||||||
NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. |
||||||
Go to Hefei city page. |