CONSTRUCTION DETAILS Start year End year Length (in km) Tunnel (in km) Tunnel Stations Source
2023 2029 1.8* 1.8 100% 1** Media
COST INFORMATION Cost (in M) Currency PPP rate Year PPP Real cost (in M$) Cost/km (in M$) Source
18700.0 HKD 0.17 2016 3152.8 1751.6 Media
REFERENCE https://news.rthk.hk/rthk/en/component/k2/1519400-20200407.htm
NOTES Sections of the line constructed in trench are represented with the same line style as the at-grade sections.
The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project.
* 1.3 km in service plus 500 m of overrun tracks at the other end.
** There’s also an at-grade infill station.