LINE Name Country City Regional Rail
Phase 1 IN Jaipur No
CONSTRUCTION DETAILS Start year End year Length (in km) Tunnel (in km) Tunnel Stations Source
2011 2020* 12.1 2.8 23% 11 Plan
COST INFORMATION Cost (in M) Currency PPP rate Year PPP Real cost (in M$) Cost/km (in M$) Source
31490.0 INR 0.06 2011 2015.4 166.6 Plan
REFERENCE http://mohua.gov.in/upload/uploadfiles/files/Jaipur_Metro_PPT.pdf
NOTES Sections of the line constructed in trench are represented with the same line style as the at-grade sections.
The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project.
* Most of the line, Phase 1A, opened in 2015.
Go to Jaipur city page.