LINE | Name | Country | City | Regional Rail | |||
Line 1 Phase 1 | CN | Lanzhou | No | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
2011 | 2016 | 26.6 | 20 | Plan | |||
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
17160.0 | CNY | 0.28 | 2012 | 4818.9 | 181.2 | Plan | |
REFERENCE | https://www.ndrc.gov.cn/fggz/zcssfz/zdgc/201209/t20120905_1145859.html | ||||||
NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. |
||||||
Go to Lanzhou city page. |