LINE Name Country City Regional Rail
Line 5 phase 2 IT Milan No
CONSTRUCTION DETAILS Start year End year Length (in km) Tunnel (in km) Tunnel Stations Source
2010 2015 6.5 6.5 100% 10 agency
COST INFORMATION Cost (in M) Currency PPP rate Year PPP Real cost (in M$) Cost/km (in M$) Source
751.0 EUR 1.3 2012 976.3 150.2 Plan
REFERENCE https://web.archive.org/web/20140508030702/http://cantieri.mit.gov.it/Lists/Scheda%20Tecnica/DispForm.aspx?ID=69&Source=http%3A%2F%2Fcantieri%2Emit%2Egov%2Eit%2FPagine%2FLombardia%2Easpx&ContentTypeId=0x01005F85B0B356E4DE4EBCF0C8A435933BF500F5F261BE3F32F347B9117D7DBB5780B0
NOTES Sections of the line constructed in trench are represented with the same line style as the at-grade sections.
The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project.