LINE Name Country City Regional Rail
M1 (Bisceglie – Baggio) IT Milan No
CONSTRUCTION DETAILS Start year End year Length (in km) Tunnel (in km) Tunnel Stations Source
2022 2027 3.3 3.3 100% 3 plan
COST INFORMATION Cost (in M) Currency PPP rate Year PPP Real cost (in M$) Cost/km (in M$) Source
396.0 EUR 1.3 2025 514.8 156.0 plan
REFERENCE https://www.comune.milano.it/aree-tematiche/mobilita/strade-e-sottosuolo/prolungamento-m1-quartiere-baggio-olmi-valsesia
NOTES Sections of the line constructed in trench are represented with the same line style as the at-grade sections.
The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project.