LINE Name Country City Regional Rail
Central Subway US San Francisco No
CONSTRUCTION DETAILS Start year End year Length (in km) Tunnel (in km) Tunnel Stations Source
2010 2021 2.7 2.7 100% 4 Media
COST INFORMATION Cost (in M) Currency PPP rate Year PPP Real cost (in M$) Cost/km (in M$) Source
1670.0 USD 1.0 2014 1670 618.5 Media
REFERENCE https://www.sfchronicle.com/bayarea/article/Central-Subway-tab-likely-to-grow-by-55M-as-14447857.php
NOTES Sections of the line constructed in trench are represented with the same line style as the at-grade sections.
The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project.