LINE | Name | Country | City | Regional Rail | |||
Jiamin | CN | Shanghai | No | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
41.6 | 35.0 | 84% | 15 | Plan | |||
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
37101.0 | CNY | 0.24 | 2018 | 8825.2 | 212.1 | Plan | |
REFERENCE | https://www.ndrc.gov.cn/fggz/zcssfz/zcgh/201812/W020190910670719961874.pdf | ||||||
NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. |
||||||
Go to Shanghai city page. |