LINE Name Country City Regional Rail
Metro NW AU Sydney No
CONSTRUCTION DETAILS Start year End year Length (in km) Tunnel (in km) Tunnel Stations Source
2013 2019 36.0 15.1 42% 13 Wiki
COST INFORMATION Cost (in M) Currency PPP rate Year PPP Real cost (in M$) Cost/km (in M$) Source
7800.0 AUD 0.69 2016 5382.0 149.5 Plan
REFERENCE https://www.transport.nsw.gov.au/news-and-events/media-releases/sydney-metro-northwest-under-budget
NOTES Sections of the line constructed in trench are represented with the same line style as the at-grade sections.
The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project.
Go to Sydney city page.