LINE Name Country City Regional Rail
Keelung MRT TW Taipei No
CONSTRUCTION DETAILS Start year End year Length (in km) Tunnel (in km) Tunnel Stations Source
2023 2032 16.0 1.6 10%* 13 Media
COST INFORMATION Cost (in M) Currency PPP rate Year PPP Real cost (in M$) Cost/km (in M$) Source
42500.0 TWD 0.07 2027 2822.0 176.4 Media
REFERENCE https://focustaiwan.tw/politics/202202220017
NOTES Sections of the line constructed in trench are represented with the same line style as the at-grade sections.
The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project.
* Approximate; imputed from station descriptions in https://www.archyde.com/the-first-phase-of-the-keelung-mrt-route-is-finalized-a-total-of-13-stations-from-badu-to-nangang-will-be-completed-as-soon-as-the-end-of-2032-politics-%E6%96%B0%E5%A4%B4%E5%A3%B3-newtalk/.