LINE | Name | Country | City | Regional Rail | |||
Line 1 phases 1-3 | IT | Turin | No | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
2000 | 2011 | 13.2 | 13.2 | 100% | 21 | agency | |
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
1,138.0 | EUR | 1.25 | 2005 | 1,973.7 | 149.5 | Plan | |
REFERENCE | http://www.otipiemonte.it/Pagine/Completo.asp?ID=86 | ||||||
NOTES | The ‘Real cost’ values have been adjusted for inflation and PPP. Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. |
||||||