LINE | Name | Country | City | Regional Rail | |||
Line 15 Phase 1 | CN | Xi’an | No | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
2020 | 2025 | 19.0 | 19.0 | 100% | 11 | Plan | |
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
12436.0 | CNY | 0.24 | 2019 | 2962.4 | 155.9 | Plan | |
REFERENCE | https://www.ndrc.gov.cn/fggz/zcssfz/zcgh/201907/W020190910670748591840.pdf | ||||||
NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. |
||||||
Go to Xi’an city page. |