LINE | Name | Country | City | Regional Rail | |||
Line 4 | CN | Xiamen | No | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
2017 | 2022 | 69.6 | 31.2 | 44% | 18 | Plan | |
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
36256.0 | CNY | 0.25 | 2016 | 9089.0 | 130.6 | Plan | |
REFERENCE | http://www.gov.cn/xinwen/2016-10/13/5118393/files/fc4eeffb973d4e0297ef1fb6bcaa4e73.pdf | ||||||
NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. |
||||||
Go to Xiamen city page. |