LINE | Name | Country | City | Regional Rail | |||
Line 3 Phase 2 | CN | Xuzhou | No | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
4 years | 6.5 | 6.5 | 100% | 5 | Plan | ||
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
5015.4 | CNY | 0.24 | 2020 | 1194.7 | 183.8 | Plan | |
REFERENCE | https://www.ndrc.gov.cn/xxgk/zcfb/tz/202002/P020200210345113822478.pdf | ||||||
NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. |
||||||
Go to Xuzhou city page. |