LINE Name Country City Regional Rail
Sukhumvit Line to Kheka TH Bangkok No
CONSTRUCTION DETAILS Start year End year Length (in km) Tunnel (in km) Tunnel Stations Source
2012 2018 12.8 0.0 0% 9 Plan
COST INFORMATION Cost (in M) Currency PPP rate Year PPP Real cost (in M$) Cost/km (in M$) Source
21904.0* THB 0.09 2007 1905.6 148.9 Plan
REFERENCE https://www.mrta.co.th/en/projectelectrictrain/bangkok-and-vicinities/greenline/
NOTES Sections of the line constructed in trench are represented with the same line style as the at-grade sections.
The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project.
* 24,549 total minus 2,645 for rolling stock.
Go to Bangkok city page.