LINE | Name | Country | City | Regional Rail | |||
Line 15 Phase 1 | CN | Beijing | No | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
2009 | 2014 | 41.4 | 27.7 | 66% | 18 | Media | |
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
18100.0 | CNY | 0.3 | 2010 | 5437.1 | 131.3 | Media | |
REFERENCE | http://finance.ifeng.com/city/bj/20101117/2902241.shtml | ||||||
NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. |
||||||
Go to Beijing city page. |