LINE | Name | Country | City | Regional Rail | |||
Line 5 Phase 1 | CN | Changsha | No | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
2014 | 2018 | 22.7 | 22.7 | 100% | 18 | Plan | |
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
15663.0 | CNY | 0.28 | 2012 | 4398.5 | 193.8 | Plan | |
REFERENCE | https://www.ndrc.gov.cn/fzggw/jgsj/zcs/sjdt/201212/t20121224_1145294.html | ||||||
NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. |
||||||