LINE | Name | Country | City | Regional Rail | |||
Line 9 Phase 1 | CN | Chongqing | No | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
2015 | 2019 | 28.23 | 21 | Media | |||
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
14712.0 | CNY | 0.27 | 2013 | 4015.3 | 142.2 | Media | |
REFERENCE | http://politics.people.com.cn/n/2013/0223/c70731-20575832.html | ||||||
NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. |
||||||
Go to Chongqing city page. |