LINE Name Country City Regional Rail
Line 14 Phase 2 CN Guangzhou No
CONSTRUCTION DETAILS Start year End year Length (in km) Tunnel (in km) Tunnel Stations Source
2017 2021 11.6 11.6 100% 7 Plan
COST INFORMATION Cost (in M) Currency PPP rate Year PPP Real cost (in M$) Cost/km (in M$) Source
9494.0 CNY 0.24 2017 2269.1 195.6 Plan
REFERENCE http://www.gov.cn/xinwen/2017-03/23/5180079/files/d764253433a944c0a620def88bf6f446.pdf
NOTES Sections of the line constructed in trench are represented with the same line style as the at-grade sections.
The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project.