LINE | Name | Country | City | Regional Rail | |||
Kombilösung | DE | Karlsruhe | Yes | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
2010 | 2021 | 4.8* | 4.8 | 100% | 6 | Plan | |
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
1457.3** | EUR | 1.3 | 2016 | 1894.5 | 394.7 | Plan | |
REFERENCE | https://www.diekombiloesung.de/haeufige-fragen.html | ||||||
NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. * 3.4 km rail tunnel, 1.4 km road tunnel. ** Source gives a range of 1,427.3-1,487.3. |
||||||
Go to Karlsruhe city page. |