LINE Name Country City Regional Rail
Kombilösung DE Karlsruhe Yes
CONSTRUCTION DETAILS Start year End year Length (in km) Tunnel (in km) Tunnel Stations Source
2010 2021 4.8* 4.8 100% 6 Plan
COST INFORMATION Cost (in M) Currency PPP rate Year PPP Real cost (in M$) Cost/km (in M$) Source
1457.3** EUR 1.3 2016 1894.5 394.7 Plan
REFERENCE https://www.diekombiloesung.de/haeufige-fragen.html
NOTES Sections of the line constructed in trench are represented with the same line style as the at-grade sections.
The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project.
* 3.4 km rail tunnel, 1.4 km road tunnel.
** Source gives a range of 1,427.3-1,487.3.