LINE Name Country City Regional Rail
Line 4 BR Rio de Janeiro No
CONSTRUCTION DETAILS Start year End year Length (in km) Tunnel (in km) Tunnel Stations Source
2010 2016 16.0 15.4 96% 7* Measured
COST INFORMATION Cost (in M) Currency PPP rate Year PPP Real cost (in M$) Cost/km (in M$) Source
10300.0 BRL 0.59 2013 6077.0 379.8 Trade
REFERENCE http://itdpbrasil.org.br/wp-content/uploads/2018/05/ITDP_PP_Linha_4_Maio_2018.pdf
NOTES Sections of the line constructed in trench are represented with the same line style as the at-grade sections.
The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project.
* Including Gávea, which is on a branch.