LINE | Name | Country | City | Regional Rail | |||
Line 4 | BR | Rio de Janeiro | No | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
2010 | 2016 | 16.0 | 15.4 | 96% | 7* | Measured | |
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
10300.0 | BRL | 0.59 | 2013 | 6077.0 | 379.8 | Trade | |
REFERENCE | http://itdpbrasil.org.br/wp-content/uploads/2018/05/ITDP_PP_Linha_4_Maio_2018.pdf | ||||||
NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. * Including Gávea, which is on a branch. |
||||||
Go to Rio de Janeiro city page. |