LINE | Name | Country | City | Regional Rail | |||
Project 63 | CL | Santiago | No | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
2013 | 2019 | 37.0 | 37.0 | 100% | 28 | Plan | |
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
3000.0* | USD | 1.7 | 2016 | 5100.0 | 137.8 | Plan | |
REFERENCE | https://www.metro.cl/files/documentos/metro-investor-201709.pdf | ||||||
NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. * The cost figure is from just before Line 6 opened but more than a year before Line 3 opened. |
||||||