LINE | Name | Country | City | Regional Rail | |||
Line 6 phase 1 | BR | Sao Paulo | No | ||||
CONSTRUCTION DETAILS | Start year | End year | Length (in km) | Tunnel (in km) | Tunnel | Stations | Source |
2015 | 2023 | 15.9 | 13.4 | 84% | 15 | Trade | |
COST INFORMATION | Cost (in M) | Currency | PPP rate | Year PPP | Real cost (in M$) | Cost/km (in M$) | Source |
9600.0 | BRL | 0.44 | 2020* | 4224.0 | 265.7 | Trade | |
REFERENCE | https://www.railjournal.com/passenger/metros/revival-of-sao-paulo-metro-line-6-orange-project-a-step-closer/ | ||||||
NOTES | Sections of the line constructed in trench are represented with the same line style as the at-grade sections. The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project. * Shifted later than the midpoint since only 15% of the project is complete as of 2019. |
||||||