LINE Name Country City Regional Rail
Sergeli Line UZ Tashkent No
CONSTRUCTION DETAILS Start year End year Length (in km) Tunnel (in km) Tunnel Stations Source
2017 2020 6.94 0.0 0% 6 Trade
COST INFORMATION Cost (in M) Currency PPP rate Year PPP Real cost (in M$) Cost/km (in M$) Source
142.2* USD 5.0** 2018 711.0 102.4 Plan
REFERENCE http://www.uzbekembassy.in/construction-of-sergeli-metro-line-to-cost-170-1-million/
NOTES Sections of the line constructed in trench are represented with the same line style as the at-grade sections.
The project maps are based on information retrieved from OpenStreetMap and our research. Please contact us if you have more accurate information regarding this project.
* 170.1 million per the most up-to-date sources, e.g. https://www.railwaypro.com/wp/tashkent-metro-extension-is-underway/. Some older sources omit some of the budget and say 82.6 million, e.g. https://kun.uz/en/news/2019/02/15/sergeli-overground-metro-will-cost-uzbekistan-80-million, mentioning also 27.9 million for rolling stock; the figure given here is 170.1-27.9.
** Approximate figure; Uzbekistan has both high inflation and rapid currency depreciation.